When undertaking an electric installation process, the member is responsible for supplying the following components and completing the final site restoration.
Service Size <320 Amp
- Meter base & or disconnect(s)
- Conduit system installed in the ground
- Concrete transformer pad (if applicable)
Service Size >320 Amp
- CT Cabinet (with Polaris lugs for each conductor)
- Conduit system installed in the ground
- Concrete transformer pad(s)
- Secondary/Service wire(s)
- 2 Bolt compression fittings installed (if applicable)