Phase 3 – Pre-Construction

  • South Central Power's crew or contractor may contact OUPS to mark all underground public utilities such as electric, gas, communications, etc.
  • South Central Power will supply easement forms, but the member project or construction manager is responsible for gathering signatures as required for the installation.
  • South Central Power may require some vegetation clearing at the owners expense.
  • South Central Power is not responsible for damages to any unmarked private or public owned facilities.

Member Checklist

During the pre-construction-phase, reference this checklist to ensure you have all the information you need.

  • Pay the invoice provided. Invoices are valid for 90 days.
  • Sign and return required notarized easements.
  • Have meter base installed and inspected by the county electrical inspector or other governing authority.
  • For underground service, SCP requires a 15 foot wide path route that is free from dirt piles, debris, and construction material.
  • South Central Power's work zone must be within 6 inches +/- of final grade
  • Notify South Central Power when all the above have been completed. After this is all complete, South Central Power's construction crews may be scheduled.