It is the members responsibility to contact operations coordinator to schedule construction.
Installation typically takes up to 15 business days after phase 3 is completed. Outages or weather may increase this time.
South Central Power's construction crews will come to the site and install facilities as designed and leave the member's site ready for final restoration by the member.
Our crew or contractor may contact OUPS to mark all underground public utilities such as electric, gas, communications, etc.
We will supply easement forms, but the member project or construction manager is responsible for gathering signatures as required for the installation.
We may require some vegetation clearing at the owners expense.
We are not responsible for damages to any unmarked private or public owned facilities.
Member Checklist
During the pre-construction-phase, reference this checklist to ensure you have all the information you need.
Pay the invoice provided. Invoices are valid for 90 days.
Sign and return required notarized easements.
Have meter base installed and inspected by the county electrical inspector or other governing authority.
Provide a path 15 foot wide (underground) or 30 foot wide (overhead) to accommodate installation
work.
South Central Power's work zone must be within 6 inches +/- of final grade
Notify South Central Power when all the above have been completed. After this is all complete, South Central Power's construction crews may be scheduled.
Note: Failure to mark the desired location of service may result in job delays and/or additional charges.
Stake all facilities.
Upon request, a field engineer will meet with you on-site to discuss options.
Next, we will perform a site visit and design the most economical route for electric service installation, place stakes marking the proposed route, and determine members cost as well as other responsibilities.
Major changes to this design may result in job delays and extra fees.
Member Checklist
During the design-phase, reference this checklist to ensure you have all the information you need.
Mark your proposed meter location.
Please stake all facilities. These Include:
Property lines
The 4 corners of the home and other proposed buildings
Underground member-owned facilities (well, septic, water lines, propane lines, sprinklers, dog fence, etc.)
This step may take 2 to 4 weeks depending on our waiting list and seasonal demands. Jobs are typically performed on a first come, first serve basis. We will contact you with any questions or follow up.
Member Checklist
During the application phase, reference this checklist to ensure you have all the information you need.
Complete application for service.
Include load information.
Indicate service size and overhead or underground preference.
Draw a site map.
Review information and sign form.
Submit application online or to any South Central Power office location.